Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
Insight
Articles
August 7, 2026 • 6-minute read
On 29 July 2026, the UK’s Office of Gas and Electricity Markets (“Ofgem”) opened a consultation (the “Consultation”) on its proposal intended to deter speculative, non-viable data centre projects from the UK’s grid connection queue. Ofgem’s key proposals include securing a substantial “returnable” (subject to project completion) commitment fee and demonstration of “genuine” progression through a series of queue management milestones covering compute offtaker demand, long-lead equipment procurement, and financial capability and technical readiness.
What is Proposed?
1. Data Centre Commitment Fee
Ofgem has proposed a lump sum Data Centre Commitment Fee of between £237,500 and £712,500 per megawatt (such final amount yet to be determined by Ofgem) which would be secured from connection offer / bilateral connection agreement acceptance (or if later, from the time the policy is implemented) and released upon energisation of the project. Critically, the fee (or part thereof) becomes payable if the project terminates, reduces capacity or fails to comply with the relevant requirements. The fee may be secured by provision of a cash deposit in a bank account, a performance bond or letter of credit from a qualified bank or a performance bond from a qualified company.
The lump sum “returnable” (subject to energisation) fee option was recommended over an incrementally returnable fee or a progression commitment fee-style model, with Ofgem scoring this option higher (despite other options having higher levels of support) partly on the basis of administrative simplicity.
The proposed queue management milestones put the commitment fee early on in the process, before even an operate, lease or sale Memorandum of Understanding (“MoU”) has been entered into. For a 100 MW project, that means securing between £23.8 million and £71.3 million at the point of accepting a connection offer, on the strength of little more than a decision to proceed.
2. Project Progress Milestones
As well as the commitment fee, developers would have to demonstrate “genuine” progress against several key milestones in order to maintain their position in the queue, including securing a credible end-user of the data centre, procurement of electrical equipment with long lead times (e.g. switchgear), and financial and technical capability to develop a data centre. If a developer cannot provide sufficient evidence at each milestone, the project is treated as having failed that requirement and may be ejected from the connection queue. Material misrepresentation, or a failure to notify the network operator that earlier evidence is no longer valid, is treated in the same way.
The milestones would sit alongside the existing National Energy System Operator (“NESO”) and Distribution Network Operator (“DNO”) queue management milestones, rather than replacing them, and would be sequenced as follows:
The timing of the proposed milestones reference existing NESO queue management milestones points, rather than by specifying fixed calendar deadlines or time periods.
Key Risks for Project Developers
1. Development Risk Capital
The most obvious risk is capital lock-up. Ofgem’s own modelling shows an internal rate of return (“IRR”) impact of up to 170 basis points for the worst case scenario. While performance bonds and letters of credit are permitted, this will consume borrowing capacity that would otherwise support construction.
2. Project Structure Inflexibility
A capacity reduction triggers a liability referable to the reduced MW, a change of use out of data centre triggers the full securitised amount as if the project had terminated. Phasing decisions therefore need to be taken before offer acceptance, not iterated during development. Once the fee policy is implemented, any self-termination after the fee applies leaves the developer liable for payment of the fee, thus potentially disincentivising self-termination at all.
3. Circularity
Project developers may have difficulty securing executed offtake agreements (as required by M6.Dc) without certainty over connection timing and financial backing requirements imposed too early create a dependency loop where financing depends on a connection date which itself depends on financing. Ofgem’s answer is staging, with non-binding evidence at M0.5.Dc and binding evidence at M6.Dc. Whether that is far enough down the development curve for a colocation platform with a multi-customer fill strategy is precisely the question Q30 and Q31 of the Consultation invite the market to answer.
The Engineering, Procurement and Construction (“EPC”) Risk Allocation Problem
A significant point of difficulty is M2.Dc, whereby Ofgem is, in substance, requiring a material procurement commitment for transformers and switchgear as a condition of retaining queue position, at a point which sits well before the M7 project commitment and final investment decision.
A Likely Accelerant for Behind-the-Meter and Private Wire Power
Ofgem identifies “speed to power” (the gap between deciding to build and securing enough power to run the compute) as a central constraint on data centre delivery. Ofgem’s proposal will make holding a public-grid queue position more expensive and more conditional. This will likely have the effect of improving the appeal of, and we expect to accelerate the level of developer interest in, behind-the-meter (“BTM”) generation, private wire arrangements and on-site microgrids for data centres. The UK, and indeed the rest of the EU, is behind the curve on the adoption of BTM solutions when compared to the US where the adoption of BTM solutions is accelerating in response to constraints on grid power availability and public backlash on data centres in local communities.
Ireland presents a clear illustration of where constraints on grid connections could lead. Faced with the restrictions on new grid connections around Dublin, and the December 2025 large energy user and private wire framework, developers there have moved on-site generation from emergency backup to primary strategy. Pure Data Centres Group’s Dublin campus is a leading example: its 110 MW on-site microgrid, integrating battery storage and billed as Europe’s first, will provide dispatchable capacity to run the facility through initial development, ahead of full grid integration. Whilst Ofgem is not intent on suspending connections, the direction of travel is the same, and a queue that is costlier and more conditional to hold pushes the economics further towards BTM and private wire arrangements.
For developers, investors and contractors, on-site generation, battery storage and microgrid controls are likely to become a key development feature, carrying their own EPC scope and costs, long-lead procurement, grid-code compliance and technical-certification demands, and their own risk-allocation debates over availability, performance and the interface with any eventual grid connection.
What Feedback Do We Anticipate?
We expect the following themes to dominate responses:
Practical Steps for Developers
Developers with projects in the queue should be modelling the fee at both ends of the range against their connection date, confirming whether security can be provided, and reviewing whether their intended commercial model maps cleanly onto the Self-operation or Lease or Sale pathway, bearing in mind that only one pathway change is permitted over the life of the project. On the contracting side, procurement strategy, novation mechanics and certification deliverables should be revisited now, on the assumption that M2.Dc and M6.Dc will land broadly as proposed. Responses to the Consultation are due by 16 September 2026.
This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.
Discover our latest:
Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
CLE Events
Sixth Annual Navigating the Annual Meeting and Reporting Season
Join leading practitioners and industry voices for a timely discussion of the legal, regulatory, and governance developments shaping the next proxy season.
November 11, 2026
November 11, 2026 • 2-minute read
Events
Jenny Speck Speaking at 2026 AFCC Global Biobased Economy Conference
Partner Jenny Speck will speak at the 2026 AFCC Global Biobased Economy Conference & Exhibit in a session titled “Tax …
November 3, 2026
November 3, 2026 • 1-minute read
Podcasts
Powering Progress Episode 14 – Environmental Litigation and the New Data Center Playbook
This series has explored the extraordinary investment flowing into data centers and the challenges surrounding power, real estate, financing, and …
October 29, 2026
October 29, 2026 • 14-minute read
Client Alerts
UK Budget 2026: Data Centres and Power Generation
The Chancellor, John Healey, promised to tackle “the big challenges in energy” with a 10 Year Plan. The Government’s headline …
October 28, 2026
October 28, 2026 • 4-minute read
Media Coverage
Stephanie Noble Featured in Energy & Mineral Law Foundation Member Spotlight
Partner Stephanie Noble was featured in the Energy & Mineral Law Foundation (EMLF) Member Spotlight, where she discussed her path …
October 28, 2026
October 28, 2026 • 1-minute read
Deals & Cases
Vinson & Elkins advised GridStor in connection with the financing of White Tank, a 100 MW / 400 MWh stand-alone …
October 28, 2026
October 28, 2026 • 1-minute read
Firm News
Vinson & Elkins Hires Corporate Partner Lisa Morales
Morales is an experienced M&A lawyer who advises major public companies, financial institutions, and private capital clients on strategic transactions. …
October 28, 2026
October 28, 2026 • 2-minute read
Deals & Cases
Vinson & Elkins Represents Perella Weinberg Partners as Financial Advisor in EQT Takeover of Qiagen
Vinson & Elkins is representing Perella Weinberg Partners as financial advisor to the Supervisory Board of Qiagen N.V. in connection …
October 22, 2026
October 22, 2026 • 1-minute read
Media Coverage
Jon Solorzano Discusses Declining Proxy Advisor Influence with FT Agenda
Vinson & Elkins Partner Jon Solorzano spoke with FT Agenda about the declining influence of proxy advisors like ISS and …
October 21, 2026
October 21, 2026 • 1-minute read
Articles
Law Is a Practice. So Is Business Development.
Randi Revisore, Lauren Alford, and DeAnna Englezos reflect on two years of success leading BD Lab — Vinson & Elkins’ …
July 14, 2026 • V&E+ | Values
July 14, 2026 • 7-minute read
Articles
Data Center Dealmakers: A New Era of Power and Compute
Vinson & Elkins Partners Creighton Smith and Milam Newby share the story behind a groundbreaking AI infrastructure transaction — and …
June 15, 2026 • V&E+ Ventures
June 15, 2026 • 5-minute read
Client Alerts
Mid-Level Mindset: Empowering Lawyers Through a Pivotal Career Stage
Vinson & Elkins’ inaugural Mid-Level Associate Summit brought lawyers from across the firm to Houston for three days of learning …
March 31, 2026
March 31, 2026 • 5-minute read
Client Alerts
Pro Bono at Vinson & Elkins: Lawyers Changing Lives
Pro Bono Counsel Parker Cragg reflects on a life dedicated to service, returning to Vinson & Elkins, and wisdom he has picked up along the way.
October 20, 2025 • V&E+ Values
October 20, 2025 • 6-minute read
Client Alerts
The Genuine Cup: Soccer Strengthens Our Communities
Vinson & Elkins Chair Keith Fullenweider and Vice Chair Hilary Preston, alongside partners Creighton Smith and Jenny Speck, sit down for conversation on a global soccer tournament, the firm’s support for it, and their experience as spectators and volunteers.
August 27, 2025 • V&E+ Values
August 27, 2025 • 7-minute read
Thoughts or questions? Send us a note, and we’ll connect you with the right person.
our People
Please note that any communication with Vinson & Elkins via e-mail through this website does not constitute or create an attorney-client relationship with V&E. Please do not send any confidential information. A conflicts-of-interest procedure must be completed by V&E prior to establishment of an attorney-client relationship. When you execute an engagement letter from V&E you will be our client, and you may then exchange information freely with a V&E attorney.
By clicking “Accept,” you agree that we may review any information you transmit to us. You recognize that our review of your information, even if it is highly confidential and even if it is transmitted in a good faith effort to retain us, does not preclude us from representing another client directly adverse to you, even in a matter where that information could and will be used against you.