Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
Insight
Client Alerts
V&E Construction Update
May 27, 2025 • 6-minute read
Last week the UK Supreme Court handed down its highly anticipated decision in URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21. The judgment provided helpful clarification on the recoverability of remediation costs voluntarily incurred, and the application of the Building Safety Act 2022 (“BSA”), the Defective Premises Act 1972 (“DPA”), and Civil Liability (Contribution) Act 1978 (the “Contribution Act”).
BDW, a property developer, engaged consultant engineering firm URS to provide structural designs for two residential developments (the “Developments”). Following the 2017 Grenfell Tower fire, BDW investigated the Developments and discovered serious defects. In 2020-2021, BDW performed remedial works on the Developments, although by then it had sold the Developments on to third parties, no claim had been made against BDW in relation to the defects by the new owners or occupiers of the Developments and any such claim would have been time-barred.
In 2020, BDW initiated a negligence claim in tort (to take advantage of the more favourable limitation period) against URS to recover the costs of remedial works undertaken to address these defects.
The Supreme Court considered the following four issues:
Issue 1
It was common ground that in principle BDW had a negligence claim against URS, as URS assumed responsibility to BDW under its professional services contract, and had breached the resulting duty of care by providing defective designs.
However, URS argued that because BDW had carried out the remedial works on developments which it no longer owned and without any legal obligation to do so, BDW had incurred the costs of those remedial works voluntarily. URS argued that English law recognised a ‘principle of voluntariness’ which rendered BDW’s loss outside the scope of URS’s duty and/or too remote.
The Supreme Court held there is no rule of law that prevented the recovery of costs in a negligence claim simply because they were ‘voluntarily’ incurred. While the issue of whether costs are voluntarily incurred may go to questions of legal causation and mitigation, this will be fact specific and there is no ’bright line rule of law rendering loss too remote or outside the scope of the duty of care in the tort of negligence’.1 In this case, the Court found it was strongly arguable that the repairs were reasonable (and so not truly voluntary in a way that breaks the causal chain or indicates a failure to mitigate).
The practical consequences of this are significant. It suggests that building owners or developers who incur costs to rectify defects, even when not under an immediate legal obligation to do so, are able to recover those costs from negligent parties, particularly where there may be safety issues at play. This might encourage developers to undertake necessary remediation work where they might not otherwise have done.
Because the Court found, on the first point in this ground, that the damage was not outside the scope of the duty of care owed by URS, the Court did not need to consider whether BDW had already accrued a cause of action in tort at the time it sold the Developments. However, in explaining its thinking the court commented on the House of Lords decision in Pirelli General Cable Works Ltd v Oscar Faber & Partners [1983] 2 AC 12 and gave a strong hint that its application could be limited going forward. The court said, obiter, that ‘“there are strong arguments of principle for accepting that there can only be an actual loss once the pure economic loss has been discovered or could reasonably have been discovered’.3
Issue 2
Section 135 BSA provides for a new 30-year limitation period for accrued claims under s.1 DPA (duty to build dwellings properly). Section 135(3) provides that the amendment to the limitation period ‘is to be treated as always having been in force’, save where that would involve a breach of a defendant’s rights under the Convention, or in respect of claims settled or determined before the commencement date. The Court noted that the retrospective effect of this, and other provisions of the BSA, was ‘central to achieving the aims and objectives of the BSA’.4
It was common ground that s.135 BSA applies to a claim brought under s.1 DPA. The issue was whether the retrospectivity of s.135(3) BSA applies to other claims which are dependent on the limitation period applicable to claims under s.1 DPA but are not actions brought under that section (i.e. in this case the claims in negligence and for contribution).
Based on the words, context and purpose of the statutory provision, the Court held that s.135(3) BSA does apply to claims which are dependent on s.1 DPA. To hold otherwise would undermine the purpose of the BSA, as while a homeowner would be able to bring a claim against a developer under the DPA, it would limit any ‘onward’ claims that the developer might make against the contractor directly responsible for the defect for contribution or in negligence.
Issue 3
This issue concerned whether URS owed a duty under s.1(1) DPA to BDW. URS argued that the purpose of the DPA was to address unfairness suffered by purchasers of new dwellings and not to protect developers, and that developers could not simultaneously owe DPA duties (to later purchasers) and be owed DPA duties (by those doing the work for the developer).
The Court held it was possible under the DPA for a developer to be both owed a duty and be a person to whom the duty is owed. The Court recognised that the policy of ensuring safe dwellings is better served if the DPA duty is widely owed.
This gives developers an additional route for recovery by way of a direct statutory cause of action, which has a 30-year limitation period, against those responsible for defects rendering dwellings unfit for habitation.
Issue 4
The Contribution Act gives a person (“D1”) who is liable for damage suffered by another person (“C”) a statutory right to recover contribution from anyone else (“D2”) who is liable for the same damage.
Here BDW claimed contribution for the repair costs from URS on the basis that BDW and URS are each liable to the homeowners for damage resulting from the defects. URS argued that as there has been no judgment or settlement between BDW and any third party, and no third party has ever asserted any claim against BDW, the right to contribution does not apply. BDW argued that the right to contribution arises as soon as C suffers damage for which D1 and D2 are each liable, even if C has not claimed or recovered compensation from either D1 or D2.
The Court held that a third interpretation was correct: the right to contribution arises when: (i) damage has been suffered by C for which D1 and D2 are each liable; and (ii) D1 has paid or been ordered or agreed to pay compensation for the damage to C. BDW carried out the repairs and the fact that there was no judgment against BDW or admission of liability or settlement between BDW and the homeowners did not prevent BDW from being able to claim contribution from URS.
The Supreme Court’s judgment gives developers a clearer path to recover remediation costs for defects from their supply chain, and may trigger a wave of fresh claims from developers who have covered the cost of safety remediation post-Grenfell. Ultimately, this decision reinforces the principle that costs should ultimately be borne by those responsible, and is aligned with the overall policy of the BSA and its related legislation.
1 Paragraph 53.
2 The Pirelli case has been used as precedent for the limitation period applicable to claims of negligent design, and that a legitimate cause of action for a negligent design accrues at the point at which physical damage to the building first occurred.
3 Paragraph 76.
4 Paragraph 87.
This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.
Discover our latest:
Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
CLE Events
Sixth Annual Navigating the Annual Meeting and Reporting Season
Join leading practitioners and industry voices for a timely discussion of the legal, regulatory, and governance developments shaping the next proxy season.
November 11, 2026
November 11, 2026 • 2-minute read
Client Alerts
After the Midterms: Preparing for a New Era of Congressional Oversight
Following the November 2026 midterm elections, Democrats will control both the House and the Senate when the 120th Congress convenes …
November 5, 2026
November 5, 2026 • 5-minute read
Client Alerts
Texas Business Court Quarterly Update – 2026 Q3 Summaries
In the third quarter of 2026, the Texas Business Court continued its progress on an ever-growing docket, issuing a number …
November 4, 2026
November 4, 2026 • 44-minute read
Client Alerts
Fifth Circuit Rejects CFIUS Preemption Challenge to Texas’s Lone Star Infrastructure Protection Act
On October 16, 2026, the United States Court of Appeals for the Fifth Circuit issued its decision in GH America …
November 3, 2026
November 3, 2026 • 9-minute read
Media Coverage
Aubrey Bishai Explains Responsible Vibe Coding and AI Innovation in Law.com
Vinson & Elkins Chief Innovation Officer Aubrey Bishai was featured in Law.com’s coverage of LegalTech Connect’s 2026 Knowledge Management & …
November 5, 2026
November 5, 2026 • 1-minute read
Deals & Cases
Vinson & Elkins Advises Southern Realty Trust Inc. in Merger with Sunrise Realty Trust, Inc.
Vinson & Elkins advised Southern Realty Trust Inc. in connection with its entry into a definitive merger agreement with Sunrise …
November 5, 2026
November 5, 2026 • 1-minute read
Deals & Cases
Vinson & Elkins represented Select Water Holdings LLC, a subsidiary of Select Water Solutions, Inc., in connection with a new …
November 4, 2026
November 4, 2026 • 1-minute read
Deals & Cases
Vinson and Elkins advised Atlas Energy Solutions ProjectCo, LLC in a $424 million committed senior secured bridge facility with Goldman …
November 3, 2026
November 3, 2026 • 1-minute read
Deals & Cases
Vinson & Elkins advised CVR Energy, Inc. (NYSE: CVI) on its definitive agreement with subsidiaries of Marathon Petroleum Corporation (NYSE: …
November 3, 2026
November 3, 2026 • 1-minute read
Articles
Innovation and Investment: The Next Frontier in Aerospace and Defense
Vinson & Elkins Partners Sebastian Tiller and Ben Heriaud sit down for a conversation on the firm’s Aerospace and Defense …
November 3, 2026
November 3, 2026 • 6-minute read
Articles
Law Is a Practice. So Is Business Development.
Randi Revisore, Lauren Alford, and DeAnna Englezos reflect on two years of success leading BD Lab — Vinson & Elkins’ …
July 14, 2026 • V&E+ | Values
July 14, 2026 • 7-minute read
Articles
Data Center Dealmakers: A New Era of Power and Compute
Vinson & Elkins Partners Creighton Smith and Milam Newby share the story behind a groundbreaking AI infrastructure transaction — and …
June 15, 2026 • V&E+ Ventures
June 15, 2026 • 5-minute read
Client Alerts
Mid-Level Mindset: Empowering Lawyers Through a Pivotal Career Stage
Vinson & Elkins’ inaugural Mid-Level Associate Summit brought lawyers from across the firm to Houston for three days of learning …
March 31, 2026
March 31, 2026 • 5-minute read
Client Alerts
Pro Bono at Vinson & Elkins: Lawyers Changing Lives
Pro Bono Counsel Parker Cragg reflects on a life dedicated to service, returning to Vinson & Elkins, and wisdom he has picked up along the way.
October 20, 2025 • V&E+ Values
October 20, 2025 • 6-minute read
Thoughts or questions? Send us a note, and we’ll connect you with the right person.
our People
Please note that any communication with Vinson & Elkins via e-mail through this website does not constitute or create an attorney-client relationship with V&E. Please do not send any confidential information. A conflicts-of-interest procedure must be completed by V&E prior to establishment of an attorney-client relationship. When you execute an engagement letter from V&E you will be our client, and you may then exchange information freely with a V&E attorney.
By clicking “Accept,” you agree that we may review any information you transmit to us. You recognize that our review of your information, even if it is highly confidential and even if it is transmitted in a good faith effort to retain us, does not preclude us from representing another client directly adverse to you, even in a matter where that information could and will be used against you.