On September 30, 2026, the chairs and ranking members of the Senate Environment and Public Works and Energy and Natural Resources Committees, a bipartisan group of senators, introduced S. 5653, the Bipartisan American Affordability and Jobs Act of 2026 (the “Bill”), a broad energy and permitting package. On November 19, 2026, the Senate passed the Bill as an amendment to H.R. 2347, a House-passed tax bill. This alert reflects the Senate-passed text, and section references below are to that version.

The provision that is likely most significant to the electric power sector is Section 2101, which rewrites Section 216 of the Federal Power Act (“FPA”), the federal “backstop” authority for siting interstate electric transmission facilities. First enacted in the Energy Policy Act of 2005 (“EPAct 2005”) and widely regarded as ineffective after the Fourth Circuit’s decision in Piedmont Environmental Council v. FERC, 558 F.3d 304 (4th Cir. 2009), the existing backstop siting framework has never been used to permit any transmission line.

Section 2101 aims to change the Federal Energy Regulatory Commission’s (“FERC”) backstop authority. It converts FERC’s backstop authority to permit interstate transmission lines from a narrow residual power, available only in corridors designated by the Department of Energy (“DOE”), into a mandatory permitting pathway for high-voltage transmission facilities in the national interest. Under the Bill, FERC would be required, rather than merely authorized, to issue a permit once it makes the required findings.

This alert summarizes the key changes and outlines the practical implications for transmission developers, incumbent utilities, public power and cooperative entities, and large-load customers. It also covers Section 2104, which would let state commissions refer a public utility to FERC for investigation of its local transmission planning, with remedies that include return-on-equity reductions and civil penalties of up to $5 million per facility, credited to the transmission customers that bore the facility’s costs. It also notes related provisions affecting interstate natural gas pipelines regulated by FERC under the Natural Gas Act. Section 2101 does not give FERC eminent domain authority of its own. As under current law, however, FPA Section 216(e) allows the holder of a FERC permit that cannot acquire a needed right-of-way by agreement to acquire it by eminent domain through a condemnation action in federal district court or the appropriate state court. Section 2101 leaves that authority in place but makes two changes: (1) it strikes the existing exclusion for property owned by a state, so that state-owned property (though not federal property) could be condemned, and (2) it provides that condemnation actions in federal court would follow Federal Rule of Civil Procedure 71.1 rather than state practice.

For analysis of the Bill’s parallel reforms to the National Environmental Policy Act of 1969 (“NEPA”), the Clean Water Act, the Endangered Species Act, and the National Historic Preservation Act (“NHPA”), see our companion V&E insight, “To the Finish Line: Ten Ways the New Senate Permitting Bill is a Boon for Energy Infrastructure.”

Eliminating the Corridor Prerequisite

Under current law, FERC’s backstop authority to permit new transmission lines is available only within geographic areas that DOE has designated as National Interest Electric Transmission Corridors (“NIETCs”), a cumbersome process that has produced only two designations in more than two decades. Section 2101 eliminates the NIETC prerequisite entirely. The revised FPA Section 216(b) authorizes FERC to issue permits for the construction or modification of electric transmission facilities “necessary in the national interest” without any prior DOE corridor designation. The DOE corridor concept is replaced by a new study process requiring DOE to identify constrained and congested geographic areas every three years (with the first study due within one year of enactment), but the study is informational only and is not a prerequisite to FERC action on a permit application.

Fixing the “Fatal Flaw”: Mandatory Authority and State Denials

The most significant structural change in the Bill is the shift from discretionary to mandatory permitting language. The revised FPA Section 216(b) provides that FERC “shall” issue a permit for the construction or modification of electric transmission facilities when it makes the required findings, replacing the permissive “may” that previously governed. In practice, if the Bill were enacted, FERC would have to issue a permit once two things are shown: (1) one of the state-action triggers in FPA Section 216(b)(1) is met (for example, the state has not acted within one year, has denied the application, or lacks authority to approve it), and (2) the project satisfies the five additional findings in FPA Section 216(b)(2)–(6), described below. FERC would still act only after notice, a hearing, and a public comment period of at least 45 days. The Bill also revises the trigger for FERC jurisdiction under FPA Section 216(b)(1)(C)(i): The one-year state-action clock (the period during which a state has to act on a siting application before FERC may step in) now runs from “the date on which the application was filed with the State commission or other entity,” eliminating the ambiguous “later of” formulation in current law, which measured the year from the later of the date the application was filed or the date DOE designated the relevant corridor. This change addresses state delay by fixing when the one-year period begins, but it does not on its face address the Piedmont problem, in which the Fourth Circuit held that an outright state denial was not a “withholding” of approval and therefore did not trigger FERC backstop jurisdiction. Congress addressed that problem in 2021, when the Infrastructure Investment and Jobs Act added a separate trigger for a state’s denial of an application. Section 2101 leaves that denial trigger in place and, by eliminating the corridor prerequisite, would make it available outside DOE-designated corridors.

New Findings FERC Must Make

In addition to the existing state-action triggers, the Bill adds five new findings that FERC must make before issuing a backstop permit to construct or modify electric transmission facilities:

  1. Interstate or foreign commerce. The facility must be used in interstate commerce (including transmission from the Outer Continental Shelf (“OCS”) to a state) or in foreign commerce.
  2. Public interest. The permit must be consistent with the public interest.
  3. Consumer protection, improved reliability, and just and reasonable rates. The facility must protect or benefit consumers, provide “improved reliability” as defined in new FPA Section 225(a), and facilitate just and reasonable rates.
  4. Voltage threshold. The facility must be capable of operating at 230 kV or above, or be necessary to safely and reliably interconnect one or more such facilities covered by the permit. An exception applies to facilities using advanced transmission conductors (including superconductors), as defined by FERC, for which FERC may set, on a project-specific basis, the voltage it determines appropriate for facilities of comparable throughput.
  5. Modification standard. Where the permit authorizes modification of existing transmission facilities (including reconductoring, meaning replacement of existing conductors with higher-capacity ones), the project must maximize, to the extent reasonable and economical, the capabilities of existing towers, structures, and rights-of-way.

The 230 kV threshold and the advanced-conductor exception are particularly relevant for developers evaluating reconductoring and grid-enhancing technology projects, which may be able to add capacity within existing rights-of-way. Section 2102 of the Bill further supports this pathway through new FPA Section 216A, which provides that activities to maintain or increase grid transmission capacity within an existing right-of-way (or the minimum adjacent area, up to one-quarter mile from the right-of-way, needed to meet electrical standards or complete the work), including reconductoring, voltage increases, circuit additions, advanced transmission technologies, storage, and parallel circuits, are neither a “major Federal action” under NEPA nor an “undertaking” under NHPA Section 106. Section 2102(b) does the same for interstate natural gas pipelines, as discussed below.

Pre-Filing Timing; Simultaneous Processing Provision Dropped

The introduced version of the Bill included a simultaneous processing provision allowing applicants for transmission facilities rated at 345 kV and above to file a FERC backstop application at the same time as, or any time after, the state siting application. The Senate-passed text does not include that provision. Instead, the Senate-passed Bill addresses only FERC’s pre-filing process, which the Bill does not define. Under the Bill, any FERC pre-filing process may begin before, but must begin no later than, the date the application is submitted to the state commission or other siting authority. Because the one-year state-action clock also runs from the state filing date, early pre-filing would allow developers to build the federal record while the state proceeding is underway. However, FERC still must make findings on the five factors described above before issuing a permit. The Bill does not specify how the start of pre-filing is to be measured or documented and leaves it to FERC to define in its implementing rules.

Preservation of State Authority and Landowner Protections

To address federalism concerns, the Bill includes several provisions designed to preserve state involvement:

  • State record consideration. States may file with FERC the parts of the record of their state siting proceeding that they consider relevant, and FERC must consider them in deciding whether to issue a permit. The Bill does not specify what weight FERC must give that record; it requires only that FERC consider it.
  • Consultation requirements. FERC must give affected states, federal agencies, Indian tribes, private property owners, and other interested persons a reasonable opportunity to present their views and recommendations on the need for and impact of the project. The Bill does not prescribe a more detailed process or require FERC to adopt those recommendations.
  • Landowner input. FERC must take into account “landowner input” from “affected landowners” (defined to include farmers and ranchers), obtained through FERC notification and consultation processes. The Bill defines “affected property” broadly to capture land crossed by or used for the facility, abutting rights-of-way within 500 feet, and residences within 500 feet of the right-of-way. The Bill requires only that FERC take landowner input into account when authorizing the project; it does not prescribe the notice and consultation procedures FERC must use or the weight the input must receive.
  • No permit without triggering findings. FERC cannot issue a permit except upon making findings on the five factors outlined above.

Expanded Jurisdiction: Public Power, Co-ops, and the ERCOT Carve-Out

New FPA Section 216(k) expands FERC’s backstop siting jurisdiction to cover all transmitting utilities, including government-owned utilities and rural electric cooperatives, with two exceptions: (1) Electric Reliability Council of Texas (“ERCOT”) utilities are excluded, and FPA Section 216 does not apply within ERCOT at all; and (2) exempt transmitting utilities (states and their political subdivisions, and electric cooperatives that receive Rural Electrification Act financing or sell less than 4 million megawatt-hours of electricity per year) that do not voluntarily submit are not covered. The Bill also provides that subjecting a government-owned or cooperatively owned electric utility to backstop siting authority does not make it a “public utility” for other FPA purposes — a firewall that confines the jurisdictional expansion to siting purposes only. In other words, FERC’s authority over these entities is limited to the purposes of FPA Section 216, which include the cost-allocation and transmission-service requirements described below, and does not make them “public utilities” subject to FERC’s general rate regulation under FPA Sections 205 and 206.

Cost Allocation and Ratepayer Protection

New FPA Section 216(f) establishes a cost-allocation framework for the costs of building and operating new or modified transmission facilities permitted. Key features include:

  • Cost-causation principle. Costs are allocated to customers that benefit, consistent with the principle that costs should be at least roughly commensurate with the benefits they receive. Recognized benefits include improved reliability, reduced congestion, reduced power losses, greater carrying capacity, reduced operating reserves, and improved access to lower-cost generation.
  • Ratepayer protection. Costs may not be involuntarily allocated to customers that receive no benefit or only trivial benefits, although voluntary agreements remain permissible.
  • Tariff filings. Transmitting utilities must file tariffs under FPA Section 205; exempt transmitting utilities must provide service under FPA Section 211A, notwithstanding the existing FPA Section 211A(c) limitations.
  • OCS facilities. Transmission facilities located on the OCS remain eligible for cost allocation if FERC makes the relevant findings.

Separately, a new FPA Section 219(b)(4)(C) authorizes incentive rate recovery for all prudently incurred costs of payments to jurisdictions impacted by facilities developed under FPA Section 216 or the new Section 225 regional/interregional planning provisions. This adds a category of recoverable costs to the existing FPA Section 219 transmission rate incentives, which allows transmission owners to recover certain costs through their FERC-approved rates. The Bill does not define “payments to jurisdictions.”

The Senate-passed text also adds cost-responsibility rules for data centers and other computational loads. At the wholesale level, Section 2107 would require FERC, within 90 days of enactment, to revise its 1994 transmission pricing policy statement so that utilities charge eligible computational load customers the embedded cost of transmission service plus a reasonable assessment of its incremental cost. Incremental costs paid would be credited to the utility’s annual transmission revenue requirement to prevent double recovery from other customers, and customers that elect non-firm service would pay less. FERC would also have to propose a rule implementing the revised policy within the same 90 days and finalize it within one year after proposing it. For facilities allocated under new FPA Section 216(f), Section 225, or Section 228, the incremental cost would be the costs assigned under those provisions. At the retail level, new FPA Section 229 would bar any portion of the retail incremental cost of serving a computational load site from being allocated to other customers, and would confirm that states may charge these customers more than that cost and credit the excess to other ratepayers.

FERC Oversight of Local Transmission Planning

Section 2104 of the Bill adds a new FPA Section 226 giving FERC oversight of local transmission planning and development. The provision applies to “local transmission facilities,” defined as facilities located solely within the retail distribution service territory or footprint of a public utility transmission provider and not selected in a regional transmission plan for cost allocation. The Section 2104 process is triggered only by a state commission referral, although the section preserves FERC’s authority under other provisions of law, and works as follows:

State referral. Within one year of enactment, FERC must establish by rule procedures allowing one or more state commissions to refer a public utility for investigation of the utility’s processes for planning, developing, and replacing local transmission facilities. The referral must identify the processes of concern, the potential harm to wholesale or retail customers, and the state commission’s prior efforts to resolve those concerns.

FERC response and investigation. Upon receiving a referral, FERC must either dismiss it as unsupported and publicly explain why, or notice the investigation for public comment and establish an investigative team made up of one or more non-decisional staff from an office designated by the FERC Chairman and up to three representatives appointed by the referring state commission. The team has all investigative authority available to FERC or its staff in proceedings under or relating to FPA Section 307.

Findings. The investigative team must issue a preliminary findings report within 120 days after FERC notices the investigation. If the team concludes that the processes used by a public utility for planning, developing, and replacing local transmission facilities are not resulting in the selection of the more efficient or cost-effective local transmission facilities, or that those processes are interfering with the processes of the relevant transmission planning region for planning, developing, and replacing regional transmission facilities, the team must issue a final report and recommendation to FERC explaining that conclusion and recommending a remedy.

Potential remedies and penalties. Within 14 business days after receiving the investigative team’s final report and recommendation, FERC must issue a notice requesting comment on the report, and FERC must issue an order within 120 days after issuing that notice. The order may require changes to the utility’s planning processes, reduce its return on equity for local transmission facilities, eliminate the presumption of prudence for those facilities, or impose another appropriate remedy. FERC may also impose a civil penalty of up to $5 million per local transmission facility, credited to the transmission customers that bore the facility’s costs, if the facility was developed or energized during the period beginning 60 days before the referral and ending on the date of the order and FERC determines that doing so was imprudent and financially harmed wholesale or retail customers in the referring state. FERC’s orders are generally subject to rehearing and judicial review.

Section 2104 does not give FERC jurisdiction over retail electricity sales. Harm to retail customers can support a referral and certain remedies, but nothing in the transmission title grants FERC authority over sales of electric energy at retail or the local distribution of electricity.

Key Takeaways and Looking Ahead

For transmission developers: Section 2101 of the Bill is the most significant expansion of federal transmission siting authority since EPAct 2005. The elimination of the corridor prerequisite, the mandatory “shall” standard, and the planning-to-permitting fast track together create a credible federal backstop for the first time, although the Senate-passed text drops the express right to file simultaneously at FERC for lines of 345 kV and above. The advanced-conductor exception and the NEPA and NHPA exemption for reconductoring and other work in existing rights-of-way (Section 2102) further lower barriers for grid-enhancing technology deployments. Developers should also note that Section 2101 leaves in place FPA Section 216(e), under which the holder of a FERC permit that cannot acquire a needed right-of-way by agreement may seek to condemn it by court order, in federal district court or the appropriate state court (provided FERC has determined that it made good-faith efforts to engage landowners early in the process), and extends that authority to state-owned property. A backstop permit would therefore carry eminent domain authority, although condemnation itself requires a court proceeding that is separate from the FERC permit proceeding, and early landowner engagement will be important.

For incumbent utilities and public power/co-ops: The expansion of jurisdiction to public power and electric cooperatives is a major change. While the “firewall” provision limits FERC’s jurisdictional expansion to siting, affected entities should evaluate their transmission planning and siting processes in light of the new federal overlay. The cost-allocation provisions, including the prohibition on involuntary allocation to non-benefiting customers, will likely be contested in the FERC proceedings that implement them. Section 2105 would also prohibit a federal right of first refusal for transmission facilities selected in a regional or interregional plan for cost allocation, except as provided in FERC rules or orders in effect on enactment. Public utilities should also expect closer scrutiny of local transmission projects. Under Section 2104, a state commission could refer a utility to FERC for investigation of how it plans, develops, and replaces local facilities, and the remedies include planning-process changes, ROE reductions, elimination of the presumption of prudence, and civil penalties of up to $5 million per facility, credited to affected transmission customers, in specified circumstances. Utilities should document why their local projects were selected over more efficient or cost-effective alternatives and how they fit with regional planning, and should address state regulators’ concerns early, since a referral must describe the state commission’s prior efforts to resolve them.

For data center and large-load customers: The Bill’s improved reliability and consumer-benefit requirements, combined with the benefits-based cost-allocation framework, cut both ways: They support the transmission large loads need, but they also direct costs to the customers that benefit from it. Large loads dependent on new transmission interconnection or delivery capacity have a strong interest in supporting backstop permit applications. As noted above, the Senate-passed text goes further on cost responsibility in two ways. First, at the wholesale level, Section 2107 would require FERC to revise its 1994 transmission pricing policy statement and to propose a rule implementing it. The revised policy would require utilities to charge eligible computational load customers the embedded cost of transmission service plus a reasonable assessment of its incremental cost. Second, at the retail level, new FPA Section 229 would bar utilities from shifting the retail incremental cost of serving a data center to other customers. It would also confirm that states may charge data centers more than that cost, require financial assurances, and allocate service through open seasons or competitive solicitations. Large loads served through local transmission facilities should also watch Section 2104, because a state referral could change how those facilities are planned and how their costs are recovered.

For all stakeholders: The Senate passed the Bill on November 19, 2026, as an amendment to H.R. 2347, but it has not yet been enacted. The House must now act on the Senate amendment, whether by agreeing to it, amending it further, or going to conference, before the measure can be sent to the President. Whatever the ultimate outcome, Section 2101 as passed by the Senate is likely to serve as a template for any transmission siting reform that advances. Stakeholders should engage now, both in the remaining legislative process and in preparing for any potential changes that would follow enactment.

Please reach out to your Vinson & Elkins team to discuss how these proposed changes to FERC’s backstop transmission siting authority may affect your projects, planning, and regulatory strategy.


This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.

Discover our latest:

Insights

Events

Kathy Pakenham Speaking at ABA’s 2026 Criminal Tax Fraud and Tax Controversy Conference

Partner Kathy Pakenham will speak at the American Bar Association’s (ABA) 2026 Criminal Tax Fraud and Tax Controversy Conference on …

December 11, 2026

December 11, 2026 • 1-minute read

Events

Paige Anderson and Vinay Prabhakar to Present on BARBRI Webinar on REIT Tax and Data Centers

Partners Paige Anderson and Vinay Prabhakar will present on BARBRI’s live video CLE program, “Formation and Operation of Data Center …

December 10, 2026

December 10, 2026 • 1-minute read

CLE Events

Texas Data Centers in a New Political Landscape: Post-Midterm Outlook

The 2026 midterm elections are changing the policy landscape for data center development in Texas.

December 3, 2026

December 3, 2026 • 1-minute read

Client Alerts

Closer to the Finish Line: What Changed in the Senate-Passed Permitting Bill and What It Means for Energy Infrastructure

On November 19, 2026, the Senate voted 62–33 to pass the Bipartisan American Affordability and Jobs Act, signaling strong bipartisan …

November 23, 2026

November 23, 2026 • 8-minute read

Articles

Non-Bank Capital in Aircraft Finance: Here to Stay

Having entered aircraft finance as banks retreated from the sector, non-bank lenders are now an established part of the market, …

November 23, 2026

November 23, 2026 • 4-minute read

News & Achievements
V&E

Get in Touch

Thoughts or questions? Send us a note, and we’ll connect you with the right person.

The ESG GC: How Your Role as Chief Legal Officer is Integral To Your Company’s ESG Efforts Background Image