Retrofitting Carbon Capture on Energy-from-Waste: Making the Systems Connect

Articles

Carbon capture can turn the energy-from-waste fleet into a source of carbon removals. Experience of EfW projects shows how well-drafted contracts can help these first retrofits succeed.

Protos and the Retrofit Challenge

Energy-from-waste (EfW) is poised to move from managing its emissions to removing carbon. Protos in Cheshire, expected to be the UK’s first full-scale EfW carbon capture project, is due to begin capturing around 370,000 tonnes of CO₂ a year and operational from mid-2029.[1]

Kanadevia Inova, the engineering, procurement and construction (EPC) contractor for the capture plant, has appointed Veolia to supply CO₂ purification units.[2] The host plant was built by a Metlen Energy & Metals and Standardkessel Baumgarte joint venture,[3] so the capture contractor must integrate with a plant it did not build.

Who Pays for a Tonne of Carbon Captured

Stored CO₂ has no established market under current policy, so revenue comes from government through a long-term contract with the Low Carbon Contracts Company that works like a contract for difference, paying for each tonne captured.[4] Payment turns on capture rate: a capture-rate of at least 80% to start payments, a sustained shortfall cuts the return element, and below 60% the contract can be terminated. As a result, the EPC capture-rate guarantee and damages regime should be set with that revenue in mind. Under the initial Waste Industrial Carbon Capture (“Waste ICC”) contracts, removal credit sales are restricted pending review, with 90% of gross sales revenue payable to the counterparty.

When the Network is Not Ready

Protos joins a forthcoming cluster: the HyNet North West pipeline network, due to operate from 2028.[5] Elsewhere, transport links may be less certain, and the UK Emissions Trading Scheme (“UK ETS”) extension to EfW has been deferred.[6]

If the capture plant is mechanically complete but the network is not, the employer generally bears the delay, as the contractor cannot control the transport and storage (T&S) operator. A common answer is relief plus deemed completion: the contractor gets time and cost relief and its exposure ends, while the employer takes over the plant, bears standby costs and defers testing until CO₂ can flow.

The Department for Energy Security and Net Zero (DESNZ) has published a policy letting the emitter under the initial Waste ICC contracts recover its irrecoverable and unavoidable out-of-pocket costs, plus capex and return payments, caused by a T&S Commissioning Delay Event.[7] The EPC relief event and deemed completion trigger should mirror the policy’s conditions (its other operational conditions precedent met and its own connection works complete), whatever their final wording, so compensation starts the day the contractor is relieved.

The Performance Interface

A capture plant can fail even when every package meets its specification. The main risk is the interface with the existing plant: flue gas varies, and gas hotter, dirtier or wetter than assumed can undermine capture-rate.

Each party’s design envelope should match at every interface, and the contracts should name the party responsible for integration, or the employer carries it by default. An EPC contractor will want back-to-back terms with the technology provider, otherwise it carries the difference; a similar gap can open between consortium partners.[8]

A capture-rate guarantee means little unless it specifies the flue gas envelope, utilities supplied and CO₂ measurement, and owners should know how far the contractor’s capped liability falls short of lost revenue. The parties should also agree in advance what happens when no single party is at fault, for example expert determination and a sliding scale of remedies.

Working on a Live Site

The contractor builds beside a running plant, and tie-ins need shutdowns, so outage windows set the programme. Retrofit sites may also lack room, and layout affects access, outages and maintenance.

In our experience, retrofit scope tends to grow as detailed engineering shows that more of the existing plant must change than front-end engineering design (FEED) assumed. New processes may need consents whose timing neither party controls, and the capture plant can only be tested while the host runs. The contract should draw the scope boundaries (battery limits) clearly, give relief for late outages, and tie testing windows to host availability.

The tie-ins draw on the host’s live systems, from flue gas and steam to controls and emissions monitoring, so a fault can reduce the host’s output or put its permit at risk. The EfW plant must keep burning waste if the capture plant trips, so the contract must say who designs, operates and pays for isolation and bypass. Host revenue may far exceed the capture contract price, so contractors will want to exclude host revenue losses, and employers should work out early what they could recover.

What EfW Disputes Tell Us

Carbon capture on EfW is new, but its likely disputes are not. Beyond the regulatory hurdles flagged in our 2026 Energy Disputes Outlook,[9] causation and suspension are already familiar from waste and construction disputes.

The first is causation. Contractors facing failed performance tests have blamed the waste, and capture contractors may blame the flue gas. In Essex County Council v UBB Waste (Essex) Ltd (No 2), a PFI waste-treatment contract allocated composition risk to the contractor within bands, yet the contractor blamed the waste mix for failed acceptance tests. The court found the plant would have failed even on in-band waste because of its own design errors.[10] Alleging causation is easier than proving it. A testing protocol and a process for what falls outside the agreed envelope can help avoid disputes escalating to formal proceedings.

On suspension, stopping work without a contractual or statutory right is highly risky and may itself be a repudiatory breach, entitling the other side to terminate. The Construction Act’s right to suspend for non-payment cannot be assumed to help: it does not cover T&S unavailability or a lack of flue gas, and the Act may not apply to an EfW or capture plant at all.[11] Negotiate an express right to suspend, with notice periods, time and cost recovery, and adjudication that does not depend on the Act.

Beyond Protos

For the retrofits that follow, employers and contractors should:

  • map interfaces before contract award, with clear responsibility for integration and specifications drawn from FEED and measured waste and flue gas data;
  • agree an express right to suspend and consider free-standing adjudication options; and
  • design acceptance tests for the integrated system, with remedies for shortfalls that have no single cause.

Here are three questions to ask early: (1) Does the EPC capture-rate guarantee match what the revenue contract requires; (2) Who is responsible for the host-plant integration and its lost revenue; and (3) If the network is late, do EPC relief and compensation start the same day.

With the right contracts and continued policy support, EfW can become a major source of UK carbon removals.


[1] Kanadevia Inova, ‘Encyclis green lights Kanadevia Inova to build UK’s first full-scale Carbon Capture facility at Protos’ (press release, 6 October 2025).

[2] Veolia, ‘Veolia to supply CO₂ purification technology for UK’s first carbon capture plant at waste-to-energy facility’ (press release, 27 October 2026).

[3] MYTILINEOS (now Metlen Energy & Metals), press release on the EPC agreement for the Protos Energy Recovery Facility (2 December 2020).

[4] Department for Energy Security and Net Zero, ‘Industrial Carbon Capture Business Models Update‘ (November 2025), at p 8 (revenue support; capital grant for initial projects only), pp 9–13 (capture-rate thresholds: 80% minimum, 60% termination threshold; a shortfall reduces the return component) and p 23 (removal credit sales restricted; 90% of gross revenue to the counterparty). Per-tonne payment: a strike price against a carbon-linked reference price, a fixed capex payment (capital and a return) and T&S charges passed through.

[5] North Sea Transition Authority, ‘£2bn HyNet carbon storage project will provide massive jobs and net zero boost’ (press release, 24 April 2025).

[6] UK ETS Authority (published by the Department for Energy Security and Net Zero), ‘UK Emissions Trading Scheme scope expansion: waste’ (consultation page, update of 26 August 2026).

[7] Department for Energy Security and Net Zero, Industrial Carbon Capture Business Models Update (November 2025), ‘T&S Connection Delay Compensation’, p 15. Policy position only: the Protos Waste ICC Contract is unpublished. Compensation is subject to exclusions; the emitter may be a capture-plant SPV (p 14).

[8] Angus Rankin and Jess Webster, ‘A Partnership of Shared Fate: The Realities and Risks of Consortiums’, Overseas Construction Association of Japan Inc. (OCAJI) Journal, Autumn 2025, Vol 64.

[9] Vinson & Elkins, ‘2026 Energy Disputes Outlook: Key Energy Arbitration and Litigation Trends from Vinson & Elkins’ (14 January 2026).

[10] Essex County Council v UBB Waste (Essex) Ltd (No 2) [2020] EWHC 1581 (TCC) (Pepperall J, 18 June 2020).

[11] Housing Grants, Construction and Regeneration Act 1996 (the “Construction Act”), s 112 (suspension for non-payment) and s 105(2)(c) (excluding plant installation on sites whose primary activity is power generation); whether it covers an EfW or capture plant depends on the facts.


This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.

Discover our latest:

Insights

Events

Jenny Speck to Speak on BARBRI Webinar

Partner Jenny Speck will speak on BARBRI’s live video CLE program, “Tax Credit Insurance for Energy Projects: PFE Exclusions, Recapture, …

November 19, 2026

November 19, 2026 • 1-minute read

Events

Kathy Pakenham and Adriana Wirtz to Speak at TEI’s IRS Roundtable

Partners Kathy Pakenham and Adriana Wirtz will examine how a leaner, more data-driven IRS is selecting and conducting large business …

November 19, 2026

November 19, 2026 • 1-minute read

Client Alerts

The SEC Proposes to Rein In Executive Compensation Disclosure

On November 13, 2026, the SEC proposed an overhaul of the executive and director compensation disclosure rules in Item 402 …

November 17, 2026

November 17, 2026 • 10-minute read

Client Alerts

Single v Multi Contracts in Nuclear Projects: The Size of the Burden

Introduction The construction of nuclear energy projects is complex and capital-intensive, and the contracting structure can significantly affect project delivery, …

November 13, 2026

November 13, 2026 • 6-minute read

Articles

State Attorneys General Widen the Antitrust Battlefield

State attorneys general are moving to the center of antitrust enforcement, with bipartisan coalitions attacking merger settlements, information-sharing arrangements, labor-market …

November 13, 2026

November 13, 2026 • 4-minute read

News & Achievements
V&E

Get in Touch

Thoughts or questions? Send us a note, and we’ll connect you with the right person.

The ESG GC: How Your Role as Chief Legal Officer is Integral To Your Company’s ESG Efforts Background Image