Carbon capture can turn the energy-from-waste fleet into a source of carbon removals. Experience of EfW projects shows how well-drafted contracts can help these first retrofits succeed.
Protos and the Retrofit Challenge
Energy-from-waste (EfW) is poised to move from managing its emissions to removing carbon. Protos in Cheshire, expected to be the UK’s first full-scale EfW carbon capture project, is due to begin capturing around 370,000 tonnes of CO₂ a year and operational from mid-2029.[1]
Kanadevia Inova, the engineering, procurement and construction (EPC) contractor for the capture plant, has appointed Veolia to supply CO₂ purification units.[2] The host plant was built by a Metlen Energy & Metals and Standardkessel Baumgarte joint venture,[3] so the capture contractor must integrate with a plant it did not build.
Who Pays for a Tonne of Carbon Captured
Stored CO₂ has no established market under current policy, so revenue comes from government through a long-term contract with the Low Carbon Contracts Company that works like a contract for difference, paying for each tonne captured.[4] Payment turns on capture rate: a capture-rate of at least 80% to start payments, a sustained shortfall cuts the return element, and below 60% the contract can be terminated. As a result, the EPC capture-rate guarantee and damages regime should be set with that revenue in mind. Under the initial Waste Industrial Carbon Capture (“Waste ICC”) contracts, removal credit sales are restricted pending review, with 90% of gross sales revenue payable to the counterparty.
When the Network is Not Ready
Protos joins a forthcoming cluster: the HyNet North West pipeline network, due to operate from 2028.[5] Elsewhere, transport links may be less certain, and the UK Emissions Trading Scheme (“UK ETS”) extension to EfW has been deferred.[6]
If the capture plant is mechanically complete but the network is not, the employer generally bears the delay, as the contractor cannot control the transport and storage (T&S) operator. A common answer is relief plus deemed completion: the contractor gets time and cost relief and its exposure ends, while the employer takes over the plant, bears standby costs and defers testing until CO₂ can flow.
The Department for Energy Security and Net Zero (DESNZ) has published a policy letting the emitter under the initial Waste ICC contracts recover its irrecoverable and unavoidable out-of-pocket costs, plus capex and return payments, caused by a T&S Commissioning Delay Event.[7] The EPC relief event and deemed completion trigger should mirror the policy’s conditions (its other operational conditions precedent met and its own connection works complete), whatever their final wording, so compensation starts the day the contractor is relieved.
The Performance Interface
A capture plant can fail even when every package meets its specification. The main risk is the interface with the existing plant: flue gas varies, and gas hotter, dirtier or wetter than assumed can undermine capture-rate.
Each party’s design envelope should match at every interface, and the contracts should name the party responsible for integration, or the employer carries it by default. An EPC contractor will want back-to-back terms with the technology provider, otherwise it carries the difference; a similar gap can open between consortium partners.[8]
A capture-rate guarantee means little unless it specifies the flue gas envelope, utilities supplied and CO₂ measurement, and owners should know how far the contractor’s capped liability falls short of lost revenue. The parties should also agree in advance what happens when no single party is at fault, for example expert determination and a sliding scale of remedies.
Working on a Live Site
The contractor builds beside a running plant, and tie-ins need shutdowns, so outage windows set the programme. Retrofit sites may also lack room, and layout affects access, outages and maintenance.
In our experience, retrofit scope tends to grow as detailed engineering shows that more of the existing plant must change than front-end engineering design (FEED) assumed. New processes may need consents whose timing neither party controls, and the capture plant can only be tested while the host runs. The contract should draw the scope boundaries (battery limits) clearly, give relief for late outages, and tie testing windows to host availability.
The tie-ins draw on the host’s live systems, from flue gas and steam to controls and emissions monitoring, so a fault can reduce the host’s output or put its permit at risk. The EfW plant must keep burning waste if the capture plant trips, so the contract must say who designs, operates and pays for isolation and bypass. Host revenue may far exceed the capture contract price, so contractors will want to exclude host revenue losses, and employers should work out early what they could recover.
What EfW Disputes Tell Us
Carbon capture on EfW is new, but its likely disputes are not. Beyond the regulatory hurdles flagged in our 2026 Energy Disputes Outlook,[9] causation and suspension are already familiar from waste and construction disputes.
The first is causation. Contractors facing failed performance tests have blamed the waste, and capture contractors may blame the flue gas. In Essex County Council v UBB Waste (Essex) Ltd (No 2), a PFI waste-treatment contract allocated composition risk to the contractor within bands, yet the contractor blamed the waste mix for failed acceptance tests. The court found the plant would have failed even on in-band waste because of its own design errors.[10] Alleging causation is easier than proving it. A testing protocol and a process for what falls outside the agreed envelope can help avoid disputes escalating to formal proceedings.
On suspension, stopping work without a contractual or statutory right is highly risky and may itself be a repudiatory breach, entitling the other side to terminate. The Construction Act’s right to suspend for non-payment cannot be assumed to help: it does not cover T&S unavailability or a lack of flue gas, and the Act may not apply to an EfW or capture plant at all.[11] Negotiate an express right to suspend, with notice periods, time and cost recovery, and adjudication that does not depend on the Act.
Beyond Protos
For the retrofits that follow, employers and contractors should:
Here are three questions to ask early: (1) Does the EPC capture-rate guarantee match what the revenue contract requires; (2) Who is responsible for the host-plant integration and its lost revenue; and (3) If the network is late, do EPC relief and compensation start the same day.
With the right contracts and continued policy support, EfW can become a major source of UK carbon removals.
[1] Kanadevia Inova, ‘Encyclis green lights Kanadevia Inova to build UK’s first full-scale Carbon Capture facility at Protos’ (press release, 6 October 2025).
[2] Veolia, ‘Veolia to supply CO₂ purification technology for UK’s first carbon capture plant at waste-to-energy facility’ (press release, 27 October 2026).
[3] MYTILINEOS (now Metlen Energy & Metals), press release on the EPC agreement for the Protos Energy Recovery Facility (2 December 2020).
[4] Department for Energy Security and Net Zero, ‘Industrial Carbon Capture Business Models Update‘ (November 2025), at p 8 (revenue support; capital grant for initial projects only), pp 9–13 (capture-rate thresholds: 80% minimum, 60% termination threshold; a shortfall reduces the return component) and p 23 (removal credit sales restricted; 90% of gross revenue to the counterparty). Per-tonne payment: a strike price against a carbon-linked reference price, a fixed capex payment (capital and a return) and T&S charges passed through.
[5] North Sea Transition Authority, ‘£2bn HyNet carbon storage project will provide massive jobs and net zero boost’ (press release, 24 April 2025).
[6] UK ETS Authority (published by the Department for Energy Security and Net Zero), ‘UK Emissions Trading Scheme scope expansion: waste’ (consultation page, update of 26 August 2026).
[7] Department for Energy Security and Net Zero, Industrial Carbon Capture Business Models Update (November 2025), ‘T&S Connection Delay Compensation’, p 15. Policy position only: the Protos Waste ICC Contract is unpublished. Compensation is subject to exclusions; the emitter may be a capture-plant SPV (p 14).
[8] Angus Rankin and Jess Webster, ‘A Partnership of Shared Fate: The Realities and Risks of Consortiums’, Overseas Construction Association of Japan Inc. (OCAJI) Journal, Autumn 2025, Vol 64.
[9] Vinson & Elkins, ‘2026 Energy Disputes Outlook: Key Energy Arbitration and Litigation Trends from Vinson & Elkins’ (14 January 2026).
[10] Essex County Council v UBB Waste (Essex) Ltd (No 2) [2020] EWHC 1581 (TCC) (Pepperall J, 18 June 2020).
[11] Housing Grants, Construction and Regeneration Act 1996 (the “Construction Act”), s 112 (suspension for non-payment) and s 105(2)(c) (excluding plant installation on sites whose primary activity is power generation); whether it covers an EfW or capture plant depends on the facts.
This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.
Discover our latest:
Events
Jenny Speck to Speak on BARBRI Webinar
Partner Jenny Speck will speak on BARBRI’s live video CLE program, “Tax Credit Insurance for Energy Projects: PFE Exclusions, Recapture, …
November 19, 2026
November 19, 2026 • 1-minute read
Events
Kathy Pakenham and Adriana Wirtz to Speak at TEI’s IRS Roundtable
Partners Kathy Pakenham and Adriana Wirtz will examine how a leaner, more data-driven IRS is selecting and conducting large business …
November 19, 2026
November 19, 2026 • 1-minute read
Client Alerts
The SEC Proposes to Rein In Executive Compensation Disclosure
On November 13, 2026, the SEC proposed an overhaul of the executive and director compensation disclosure rules in Item 402 …
November 17, 2026
November 17, 2026 • 10-minute read
Client Alerts
Single v Multi Contracts in Nuclear Projects: The Size of the Burden
Introduction The construction of nuclear energy projects is complex and capital-intensive, and the contracting structure can significantly affect project delivery, …
November 13, 2026
November 13, 2026 • 6-minute read
Articles
State Attorneys General Widen the Antitrust Battlefield
State attorneys general are moving to the center of antitrust enforcement, with bipartisan coalitions attacking merger settlements, information-sharing arrangements, labor-market …
November 13, 2026
November 13, 2026 • 4-minute read
Deals & Cases
Vinson & Elkins Represents Double Eagle in Sale of Midland Basin Assets to Diamondback Energy
Vinson & Elkins represented Double Eagle IV Midco, LLC and Double Eagle V Midco, LLC (together “Double Eagle”) in entering …
November 16, 2026
November 16, 2026 • 1-minute read
Media Coverage
Vinson & Elkins Partner Joyce Adetutu joined CorpGov on the inaugural episode of Beyond the Boardroom, a new series co-produced …
November 9, 2026
November 9, 2026 • 1-minute read
Deals & Cases
Vinson & Elkins Advises Underwriters on Enterprise Products’ $1.5 Billion Senior Notes Offering
Vinson and Elkins advised the underwriters in connection with Enterprise Products Operating LLC’s (“EPO”) public offering of $1.5 billion aggregate …
November 6, 2026
November 6, 2026 • 1-minute read
Media Coverage
Aubrey Bishai Explains Responsible Vibe Coding and AI Innovation in Law.com
Vinson & Elkins Chief Innovation Officer Aubrey Bishai was featured in Law.com’s coverage of LegalTech Connect’s 2026 Knowledge Management & …
November 5, 2026
November 5, 2026 • 1-minute read
Deals & Cases
Vinson & Elkins Advises Southern Realty Trust Inc. in Merger with Sunrise Realty Trust, Inc.
Vinson & Elkins advised Southern Realty Trust Inc. in connection with its entry into a definitive merger agreement with Sunrise …
November 5, 2026
November 5, 2026 • 1-minute read
Articles
Innovation and Investment: The Next Frontier in Aerospace and Defense
Vinson & Elkins Partners Sebastian Tiller and Ben Heriaud sit down for a conversation on the firm’s Aerospace and Defense …
November 3, 2026
November 3, 2026 • 6-minute read
Articles
Law Is a Practice. So Is Business Development.
Randi Revisore, Lauren Alford, and DeAnna Englezos reflect on two years of success leading BD Lab — Vinson & Elkins’ …
July 14, 2026 • V&E+ | Values
July 14, 2026 • 7-minute read
Articles
Data Center Dealmakers: A New Era of Power and Compute
Vinson & Elkins Partners Creighton Smith and Milam Newby share the story behind a groundbreaking AI infrastructure transaction — and …
June 15, 2026 • V&E+ Ventures
June 15, 2026 • 5-minute read
Client Alerts
Mid-Level Mindset: Empowering Lawyers Through a Pivotal Career Stage
Vinson & Elkins’ inaugural Mid-Level Associate Summit brought lawyers from across the firm to Houston for three days of learning …
March 31, 2026
March 31, 2026 • 5-minute read
Client Alerts
Pro Bono at Vinson & Elkins: Lawyers Changing Lives
Pro Bono Counsel Parker Cragg reflects on a life dedicated to service, returning to Vinson & Elkins, and wisdom he has picked up along the way.
October 20, 2025 • V&E+ Values
October 20, 2025 • 6-minute read
Thoughts or questions? Send us a note, and we’ll connect you with the right person.
our People
Please note that any communication with Vinson & Elkins via e-mail through this website does not constitute or create an attorney-client relationship with V&E. Please do not send any confidential information. A conflicts-of-interest procedure must be completed by V&E prior to establishment of an attorney-client relationship. When you execute an engagement letter from V&E you will be our client, and you may then exchange information freely with a V&E attorney.
By clicking “Accept,” you agree that we may review any information you transmit to us. You recognize that our review of your information, even if it is highly confidential and even if it is transmitted in a good faith effort to retain us, does not preclude us from representing another client directly adverse to you, even in a matter where that information could and will be used against you.