Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
Insight
Articles
Published by Energy Intelligence, December 2025
October 28, 2025 • 6-minute read
While nuclear energy is currently being championed for its low-carbon electricity generation and energy security, the construction of facilities to provide such energy is no easy feat. From regulatory hurdles to technical complexities, navigating the construction phase of nuclear power plants demands careful consideration and proactive risk management. The average nuclear power plant (“NPP”) has a construction cost overrun of 102.5% and projects that commenced construction between 2010 and 2020 were delivered an average of three years late.1
This is made all the more difficult in light of the fact that there is no one single contractual precedent for nuclear energy projects, meaning that parties are required to either adapt existing forms or draft their own entirely. The contract used for the Hinkley Point C project, for example, used a combination of FIDIC and NEC contracts.2 Meanwhile, progress on the project itself has been far from ideal, with recent comments describing the project as “almost unbuildable”,3 and updates from EDF noting that the plant was not expected to be operational before 2030 (the original target was 2025) and the overall cost had been revised to between £31 billion to £34 billion (up from the original estimate of £18 billion).4 Even best laid plans can run into problems.
Generally, these problems can fall into one of three broad categories:
However, it is important to remember that many problems can be avoided, or at the very least mitigated in some way, to reduce the potential impact of issues and overrun of both costs and time, and to maintain the relationship between the parties, allowing the project to continue. This article will focus on the first two categories, the types of issues which may arise, and suggestions on how to mitigate them.
Pre-Construction: Regulatory, Permitting and Planning Challenges
One of the primary hurdles in NPP construction is navigating the complex web of local, national and international regulations and permitting requirements, including environmental regulations; radiation regulations; health and safety regulations; siting regulations; and export control regulations.
How to mitigate
Construction: Technical Complexity and Design Challenges
The intricate design and engineering requirements of NPPs also pose significant technical challenges during construction, particularly in circumstances where many NPPs are ‘First Of A Kind’ (rather than ‘Nth Of A Kind’), meaning that there is no prior design or existing equipment that can be used, and almost everything needs to be designed and manufactured from scratch. This means it takes much longer to design and acquire the required parts, with replacements difficult, time consuming, and costly to come by. For example, a shortage of qualified manufacturers contributed to the delays on the Olkiluoto-3 project, exacerbating pre-existing delays.10
How to mitigate
The Flamanville NPP project, for example, faced several defects challenges which contributed to significant costs increases and delays.11 EDF estimated that rectifying weld defects alone would increase construction costs by €1.5 billion, delay fuel loading, and prevent revenues from being generated in 2020 from the test phase.12
Mitigating Disputes
Should a dispute arise (either during the construction or operational phase), the parties will also want to ensure that the contract contains a detailed claims resolution procedure.
It would be prudent to include a claims notification procedure that addresses the following:
The more information that can be shared between the parties as to the nature and context of the dispute, the better understanding the parties have of the issue, and the more likely claims can be understood and resolved quickly to the parties’ satisfaction. This is particularly key in projects such as NPPs where there are long build times as well as defects liability periods and ongoing servicing; the parties will likely want to maintain relationships insofar as possible for continuity.
When drafting dispute resolution clauses, parties may wish to keep in mind that NPP projects are a prime candidate for use of multi-tier dispute resolution (“MTDR”) clauses. Under MTDR clauses, the parties agree to undertake at least one round of steps to resolve the dispute prior to resolution in arbitration or by the courts. This may include:
This can help resolve a dispute in a manner that both preserves the commercial relationship between the parties and avoids the time, disruption and cost of litigation or arbitration.
*Tom Osborn is a trainee solicitor in the London office.
1Sovacool, B. and Hanee, R., ‘Beyond economies of scale: Learning from construction cost overrun risks and time delays in global energy infrastructure projects’ (May 2025) Energy Research & Social Science, vol. 123; International Energy Agency, Electricity 2024: Analysis and forecast to 2026 (May 2024), p. 49.
2https://www.fidic.org/node/42222.
3https://www.ft.com/content/ee89bce2-a3e9-48ed-82eb-85916eb24777.
5For further information regarding the GDA process: https://www.velaw.com/insights/smrs-the-gda-process/.
7https://www.gov.uk/government/consultations/alternative-routes-to-market-for-new-nuclear-projects.
8https://www.legislation.gov.uk/uksi/2022/853/contents/made.
9R (on the application of Together Against Sizewell C Limited) v (1) Secretary of State for Energy Security and Net Zero and (2) Sizewell C Limited [2023] EWCA Civ 1517.
11https://www.reuters.com/article/edf-nuclearpower-flamanville/update-1-french-regulator-clears-edfs-flamanville-reactor-despite-weak-spots-idUSL8N1MM4QE/; https://www.reuters.com/article/edf-flamanville/update-2-edfs-flamanville-nuclear-plant-faces-new-delay-over-faulty-welding-idUSL8N23R0V8/.
This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.
Discover our latest:
Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
CLE Events
Sixth Annual Navigating the Annual Meeting and Reporting Season
Join leading practitioners and industry voices for a timely discussion of the legal, regulatory, and governance developments shaping the next proxy season.
November 11, 2026
November 11, 2026 • 2-minute read
Client Alerts
After the Midterms: Preparing for a New Era of Congressional Oversight
Following the November 2026 midterm elections, Democrats will control both the House and the Senate when the 120th Congress convenes …
November 5, 2026
November 5, 2026 • 5-minute read
Client Alerts
Texas Business Court Quarterly Update – 2026 Q3 Summaries
In the third quarter of 2026, the Texas Business Court continued its progress on an ever-growing docket, issuing a number …
November 4, 2026
November 4, 2026 • 44-minute read
Client Alerts
Fifth Circuit Rejects CFIUS Preemption Challenge to Texas’s Lone Star Infrastructure Protection Act
On October 16, 2026, the United States Court of Appeals for the Fifth Circuit issued its decision in GH America …
November 3, 2026
November 3, 2026 • 9-minute read
Thoughts or questions? Send us a note, and we’ll connect you with the right person.